MEP Co-ordination High School

MEP Co-ordination High School

Project Name: High School

Project Scope of Work: MEP co-ordination with Architectural Structural discipline. Develop shop drawings for all disciplines.

Size of Project: Medium Size project.

Area: 1, 12,680 sq.ft

Resources Utilized: 2 MEP Modelers.

Leadership: 1 Project Manager

Turn Around time: 20 working days

Project Description: Scope of work for this project was to work on MEP co-ordination and development of shop drawings for a high school.

Building Details: 2 storied Building

Inputs provided by client: Architecture, structure and MEP Models

Work Methodology:

  • Detect Clashes and resolve them through design co-ordination with Design and Engineering team.
  • Co-ordinate all seven trades (Architecture,structure, HVAC Electrical and Plumbing) together initially.
  • Generation of Shop Drawings.

Deliverables:

  • Clash report for the project
  • Co-ordinated Revit Model
  • Shop Drawings(2d Format)